i have solved my MILP problem using intlinprog, that part was fine. I am now extending the same problem but now it is depedent on time (i.e. I was to solve the optimization problem for each hour time step).
my question is: How do I extend my objective function and constraints to be time depedent?
thank you
  9 Commenti
sibabalo noludwwe
sibabalo noludwwe il 14 Apr 2020
Thanks ill try that. May you refer me to a matlab site of how i can achieve to use my previous results for the next if possible
Ameer Hamza
Ameer Hamza il 14 Apr 2020
Please see my answer below for explanation.

Accedi per commentare.

Risposta accettata

Ameer Hamza
Ameer Hamza il 14 Apr 2020
I have modified this example from the documentation: https://www.mathworks.com/help/optim/ug/intlinprog.html#mw_cd504ff9-629b-402f-acb0-7aa7c7926290 to explain the effect of using the solution from the previous time step as an initial point for the next iteration. In the following example, I used a for loop to solve an MILP problem 20 times, each time slightly varying the objective function.
First, check the code which does not use the solution from the last iteration as an initial guess of next iteration. The initial guess is always the same.
Aeq = [22 13 26 33 21 3 14 26
39 16 22 28 26 30 23 24
18 14 29 27 30 38 26 26
41 26 28 36 18 38 16 26];
beq = [ 7872
10466
11322
12058];
N = 8;
lb = zeros(N,1);
intcon = 1:N;
f = [2 10 13 17 7 5 7 3];
x0 = [8 62 23 103 53 84 46 34];
opts = optimoptions('intlinprog', 'Display', 'off');
tic
for i=1:20
f(3:5) = randi([1 15], 1, 3); % objective function is changed in each iteration
[x2,fval2] = intlinprog(f,intcon,[],[],Aeq,beq,lb,[],x0,opts);
end
toc
Time of execution
Elapsed time is 24.518613 seconds.
The following code update the initial guess
Aeq = [22 13 26 33 21 3 14 26
39 16 22 28 26 30 23 24
18 14 29 27 30 38 26 26
41 26 28 36 18 38 16 26];
beq = [ 7872
10466
11322
12058];
N = 8;
lb = zeros(N,1);
intcon = 1:N;
f = [2 10 13 17 7 5 7 3];
x0 = [8 62 23 103 53 84 46 34];
opts = optimoptions('intlinprog', 'Display', 'off');
tic
for i=1:20
f(3:5) = randi([1 15], 1, 3);
[x2,fval2] = intlinprog(f,intcon,[],[],Aeq,beq,lb,[],x0,opts);
x0 = x2;
end
toc
Time of execution
Elapsed time is 8.489186 seconds.
This example shows a speed gain of about 3 times. The actual gain can vary from problem to problem, but still, it is better than just using a random initial guess.
  19 Commenti
Ameer Hamza
Ameer Hamza il 30 Apr 2020
This is quite strange behavior. I couldn't see any reason why this should be happening. I recommend starting two instances of MATLAB and run both code line by line. You will definitely see the difference at some point.
sibabalo noludwwe
sibabalo noludwwe il 1 Mag 2020
I am running the same code i just comment the for loop and bring it back in. So its the code

Accedi per commentare.

Più risposte (1)

sibabalo noludwwe
sibabalo noludwwe il 30 Apr 2020
LP: Optimal objective value is -4.403333.
Branch and Bound:
nodes total num int integer relative
explored time (s) solution fval gap (%)
3 1.95 1 -3.750000e+00 9.403509e+00
4 2.67 2 -3.930000e+00 5.409060e+00
5 3.13 2 -3.930000e+00 0.000000e+00
Optimal solution found.
Intlinprog stopped because the objective value is within a gap tolerance of the optimal value,
options.AbsoluteGapTolerance = 0 (the default value). The intcon variables are integer within tolerance,
options.IntegerTolerance = 1e-05 (the default value).
Number of critical loads restored = 3.930000
Control variables =
Columns 1 through 11...... and so on
for the other time ste this is the solution
No feasible solution found.
Intlinprog stopped because no point satisfies the constraints.
Number of critical loads restored =
Control variables =

Categorie

Scopri di più su Get Started with Optimization Toolbox in Help Center e File Exchange

Community Treasure Hunt

Find the treasures in MATLAB Central and discover how the community can help you!

Start Hunting!

Translated by