Direct duty cycle control in MPPT

11 visualizzazioni (ultimi 30 giorni)
Hello ! I am generating a Vmpp using a Neural network and want the MPPT to output Vdc equivalent to this Vmpp. For this purpose I need to input a duty cycle into the Boost converter. I am using the formula d=1-(Vdc/Vmpp) But the duty cycle does not follow this formula and takes the value of the duty cycle to 1 (it always maxes out). Kindly guide me if I am using the right technique to control the Duty cycle or not

Risposta accettata

Sebastian Castro
Sebastian Castro il 19 Set 2017
Yeah, the problem here is you're measuring Vdc incorrectly.
Vdc isn't the measured DC link voltage on the output side... it's the DC voltage at the source (PV Array) on the left side of the boost converter.
- Sebastian
  3 Commenti
DAUDA DUNCAN
DAUDA DUNCAN il 16 Apr 2020
I am building a Buck DC DC Converter but interfacing Neural Network Subsystem and the Converter is my challenge.
Please can anybody assist?

Accedi per commentare.

Più risposte (1)

Michael  Osumune
Michael Osumune il 9 Giu 2018
Hi,
I am really confused on how to create a custom neural network. Should I build it using neural network toolbox first then import or build while in simulink. Need help guys urgently.
Thanks
  3 Commenti
DAUDA DUNCAN
DAUDA DUNCAN il 16 Apr 2020
Hello Haider,
Please I want to interface my Neural Network Subsystem with my Buck Converter but the setting of the parameters in the Simulink is my big problem.
Please could you assist me?

Accedi per commentare.

Community

Più risposte nel  Power Electronics Control

Categorie

Scopri di più su Solar Power in Help Center e File Exchange

Community Treasure Hunt

Find the treasures in MATLAB Central and discover how the community can help you!

Start Hunting!

Translated by