I have a problem in implementing ramp rate constraint using linprog function. I have 5 generators with marginal costs, ramp rate limits, min and max generation capacities as linear functions. In short my economic dispatch problem is as follows:
f = [1000 500 0 0 300]; %%Objective function
lb = [0 0 0 0 0]; %%Lower boundary
ub = [5000 9000 3500 1500 8000]; %%Upper boundary
Aeq = [1 1 1 1 1]; %%Equality Constraint
beq = L; %%Total load
Now, the ramp rate constraint: let PG1 be power generated by generator 1(say)
|PG1(k) - PG1(k-1)| <= Ramp rate limit(200);
where k is the optimization period. so how can i implement this using linprog function...?
PG = linprog(f,A,b,Aeq,beq,lb,ub);
  2 Commenti
Matt J
Matt J il 17 Nov 2017
Modificato: Matt J il 17 Nov 2017
What are the unknown variables x(i) and what is the dependence of PG on these variables?
Swaroop Mahasiva
Swaroop Mahasiva il 17 Nov 2017
Modificato: Matt J il 18 Nov 2017
PG = linprog(f,A,b,Aeq,beq,lb,ub);
Instead of x, i used PG. The output values are Power generated by each generator (PG). So x(i) = PG(i).

Accedi per commentare.

Risposta accettata

Torsten
Torsten il 20 Nov 2017
Modificato: Torsten il 20 Nov 2017
f = [1000 500 0 0 300]; %%Objective function
A = [];
b = [];
Aeq = [1 1 1 1 1]; %%Equality Constraint
beq = L; %%Total load
lb = [0 0 0 0 0]; %%Lower boundary
ub = [5000 9000 3500 1500 8000]; %%Upper boundary
PG = linprog(f,A,b,Aeq,beq,lb,ub);
A = [eye(5);-eye(5)];
for i=1:288
b = [200+PG(1) ; 83.33+PG(2) ; 100+PG(3) ; 150+PG(4) ; 66.67+PG(5) ; 200-PG(1) ; 83.33-PG(2) ; 100-PG(3) ; 150-PG(4) ; 66.67-PG(5)];
PG = linprog(f,A,b,Aeq,beq,lb,ub);
end
Best wishes
Torsten.
  4 Commenti
Swaroop Mahasiva
Swaroop Mahasiva il 9 Gen 2018
Torsten's solution satisfies ramp limits and my goal is to optimize the total generation across all 288 periods.How can i obtain optimal solution to my problem.Please help me.Thanks in advance.
Matt J
Matt J il 9 Gen 2018
Modificato: Matt J il 9 Gen 2018
What advice is there to add beyond the solution that I proposed in my answer from November?

Accedi per commentare.

Più risposte (1)

Matt J
Matt J il 18 Nov 2017
Modificato: Matt J il 18 Nov 2017
n=numel(f);
D=diff(eye(n));
A=[D;-D];
b=200*ones(n,1);
PG = linprog(f,A,b,Aeq,beq,lb,ub);
  4 Commenti
Aleksandra Komorowska
Aleksandra Komorowska il 21 Feb 2020
Hi,
I'm trying to use this code, but the following error is displayed:
The number of rows in A must be the same as the number of elements of b.
f = [1000 500 0 0 300]; % Objective function
lb = [0 0 0 0 0]; % lower bound
ub = [5000 9000 3500 1500 8000]; % upper bound
L = 20000; % load
D=speye(288);
A=kron([D,-D],eye(5));
b=kron(ones(288*2,1), [200;83.33;100;150;66.7]);
Aeq=kron(speye(288),ones(1,5));
beq=L*ones(288,1);
LB=repmat(lb(:),1,288);
UB=repmat(ub(:),1,288);
F=repmat(f(:),1,288);
PGall = linprog(F,A,b,Aeq,beq,LB,UB)
Do you have any ideas, why?
Best regards,
Aleksandra
Matt J
Matt J il 21 Feb 2020
Modificato: Matt J il 21 Feb 2020
It's because the A and b matrix generated by the code have different numbers of rows. But never mind. Looking back at it now, the problem was probably stated incorrectly. Since there are no changes in any of the problem data from period to period, satisfying the rate constraint is trivial. Just solve the optimization problem for the first period and use that for all later periods.