my objective is to minimize the settling time....so at each and every time have to calculate settling time...for that am using stepinfo syntax
result is coming like below
S = RiseTime: 0.0015
SettlingTime: 17.4555
SettlingMin: 48.2799
SettlingMax: 50.7285
Overshoot: 1.4607
Undershoot: 0
Peak: 50.7285_
PeakTime: 5.9900
so how can i take settlingTime or any value to another variable
am grateful to u if u respond _____________THANKING YOU

Risposta accettata

Birdman
Birdman il 1 Dic 2017
Consider this approach:
Gs=tf(1,[1 1]);
result=stepinfo(Gs);
SettlingTime=result.SettlingTime